The Świna tunnel by the numbers: a TBM, 6,280 segments and ground freezing

The first fixed link between the islands of Usedom and Wolin: the TBM 'Wyspiarka' bored about 8 m a day, and an escape passage was dug in frozen ground. Numbers, a timeline, the cost per metre and a comparison with Fehmarnbelt.

The Świna tunnel by the numbers: a TBM, 6,280 segments and ground freezing

On 30 June 2023 the tunnel under the Świna river opened in Świnoujście, north-west Poland: the first fixed road link between the islands of Usedom and Wolin, on which the town stands. Before that, residents and tourists depended on ferries. The tunnel was bored by the largest tunnel boring machine (TBM) ever used in a Polish tunnel, and one of its escape passages was dug in ground frozen for several months. In the BrikBeam episode (Polish audio), Brik and Bzyk show it in motion. Here we collect the numbers, the timeline and what the project means for an ordinary builder.

The data come from the fact sheet behind the episode (checked on 5 Nov 2026): publications by the contractor PORR, releases from GDDKiA (Poland's national roads authority) and the trade press. The full list of sources is at the end.

Key numbers at a glance

  • 1,780 m of tunnel, 1,484 m of it bored by the TBM; the whole route is about 3.2 km (Nowoczesne Budownictwo Inżynieryjne 4/2023; PORR, 30 Jun 2023).
  • Ø 13.46 m: the diameter of the TBM "Wyspiarka", the largest TBM used in a Polish tunnel (NBI 4/2023; inzynierbudownictwa.pl).
  • 785 rings × 8 segments = 6,280 segments (GDDKiA/gov.pl, 12 Aug 2021; inzynierbudownictwa.pl).
  • About 38 m below sea level: the tunnel's lowest point, roughly halfway along (money.pl, 3 Nov 2021; gov.pl).
  • PLN 913.8 million gross, up to PLN 775 million (85%) of it from the EU, or about PLN 0.51 million per metre of tunnel (NBI 4/2023; gov.pl; PAP).

▶ From our YouTube channel

Zamrozili ziemię, żeby zrobić drzwi w tuneluBrik and Bzyk do the maths on megastructures — an episode about the Świna tunnel and ground freezing. Audio in Polish. Watch on YouTube ↗

How "Wyspiarka" bored the tunnel

A TBM is an underground tunnel factory: at the front a rotating cutterhead excavates the ground, and at the back the machine itself builds the lining from precast reinforced concrete segments. Eight segments make one ring. "Wyspiarka" ("the Islander") was 105 m long, about the length of a football pitch, and arrived by sea from China in autumn 2020 (inzynierbudownictwa.pl; tunnelbuilder).

Cross-section diagram of the Świna tunnel: from Usedom to Wolin under the shipping lane, lowest point about 38 m below sea level
Tunnel cross-section (diagram, vertical scale exaggerated). Sources: NBI 4/2023 (PORR), PORR (30 Jun 2023), GDDKiA/gov.pl (2021), money.pl (3 Nov 2021), inzynierbudownictwa.pl.

It worked 24/7 as a slurry machine, because it passed through fine marine sand and clay mixed with gravel and chalk (conadrogach.pl; Poland at Sea). GDDKiA's releases show the progress well:

Boring progress chart: start in March 2021, 742 m on 13 July, 1,000 m on 12 August, 1,484 m in September 2021
Boring progress in 2021. Sources: GDDKiA/gov.pl (13 Jul 2021, 12 Aug 2021), Bankier, inzynierbudownictwa.pl; average: our calculation.
Date Stage Sources
Mar 2021 boring starts from the Usedom side Bankier; GDDKiA
13 Jul 2021 halfway: 742 m, 417 rings GDDKiA/gov.pl
12 Aug 2021 1,000 m, 484 m to go GDDKiA/gov.pl
Sep 2021 TBM in the reception shaft on Wolin GDDKiA; Bankier
30 Jun 2023 tunnel opens PORR; NBI 4/2023

How we worked it out: 1,484 m in about 190 days gives an average of about 8 m a day. Each ring is a set of segments that have to be delivered, lifted and fitted; 785 rings in about 190 days means about 4 rings a day.

Ground freezing: a door in a tunnel under the riverbed

The most unusual part of the project was the passage to the escape gallery under the roadway. To dig it in waterlogged ground, the surrounding soil was frozen with brine at about −35 °C. Active freezing, which builds the "ice shell", took about 40 days, and maintenance freezing during the works about 100 days, about 5 months in total (money.pl, 3 Nov 2021; inzynierbudownictwa.pl).

Chart: active freezing about 40 days, maintenance freezing about 100 days, about 5 months in total
Ground-freezing time for the escape passage. Sources: money.pl (3 Nov 2021), inzynierbudownictwa.pl, NBI 4/2023.

Ground freezing is used when something has to be dug in water-saturated soil that cannot be stabilised any other way. The frozen water in the pores acts as a binder and a seal at the same time. It is slow and expensive but predictable, so it is used locally: for cross-passages, shafts and connections to existing structures.

Inside the Świna tunnel: roadway, lighting and a car driving into the tunnel
Inside the Świna tunnel. Photo: TrainSimFan, CC BY-SA 4.0, Wikimedia Commons (source); number plate blurred by the editors.

How to work out the spoil from a TBM: a worked example

The cutterhead diameter lets you estimate how much ground had to come out:

  1. Cross-section area: π × (13.46 m ÷ 2)² ≈ 142.3 m².
  2. Volume over the bored length: 142.3 m² × 1,484 m ≈ 211,000 m³ of ground in situ (our calculation).
  3. Per day: 211,000 m³ ÷ about 190 days ≈ 1,100 m³ a day.
  4. For scale: if this ground were trucked away in 8 m³ loads, it would take over 26,000 trips, and excavated soil bulks up, so more in practice.

In a slurry TBM the spoil is mixed with the slurry and pumped through a pipeline to a separation plant on the surface, where the soil is removed and the slurry goes back into circulation. That is why boring under the shipping lane could carry on non-stop, with no trucks at the tunnel face.

The same arithmetic is useful for a house dig: excavation volume × bulking factor = how many tipper loads to order.

Bored or immersed: which method when

Feature Bored (Świna) Immersed (Fehmarnbelt, Drogden)
How it is built TBM under the bed, segmental lining elements cast on land, sunk into a trench
Shipping during works uninterrupted, the machine works under the bed works in the trench on the shipping lane, time windows
Depth can go deep (here about 38 m below sea level) trench in the seabed, down to about 40 m below the surface
When it pays off shorter crossings, busy waterways long crossings, shallow seas, wide sections (road + rail)

Sources for the parameters: NBI 4/2023, money.pl (3 Nov 2021), Femern A/S (2026). The comparison of methods is our general summary, not an analysis of a specific project.

The money: what a metre of tunnel costs

The project cost PLN 913.8 million gross, of which up to PLN 775 million (85%) came from EU funds (NBI 4/2023; gov.pl; PAP). Per metre of tunnel: PLN 913.8 million ÷ 1,780 m ≈ PLN 0.51 million per metre. That is a simplification, because the figure also covers the access roads and the whole route of about 3.2 km, but it shows the scale.

The road to construction was long. A tunnel construction committee was set up in 1996, PLN 2 million for a study appeared in the 2007 budget, and the first contractor chosen, Astaldi, withdrew in August 2018. The contract with PORR was signed in September 2018 (Interia; Demagog; PORR). The pandemic delayed delivery and assembly of the TBM by 95 days, pushing the opening from autumn 2022 to June 2023 (Eurobuild CEE; Bankier).

What the tunnel changed

The ferry crossing took about 40 minutes without a queue, and in summer the queues ran to hours. Driving through the tunnel takes a few minutes (Interia; NBI 4/2023). The traffic lanes are 3.5 m wide, with hard shoulders of about 2 m (money.pl). The Bielik ferries have not disappeared completely; the Warszów crossing now mainly serves pedestrians and cyclists, and the Bielik III ferry was put up for sale with an asking price of PLN 5,040,800 net (TVP Info; Interia).

The Bielik IV ferry crossing the Świna river, with Świnoujście in the background
The Bielik IV ferry on the Świna. Photo: Kapitel, CC BY-SA 4.0, Wikimedia Commons (source).

The Świna tunnel compared with others

The Świna tunnel is bored, not immersed like the tunnels under the Øresund or the Fehmarn Belt. For scale: Fehmarnbelt will be about 18 km long, about 10 times as long (Femern A/S). More on immersed tunnels in the Fehmarnbelt tunnel by the numbers.

Bar chart of tunnel lengths: Fehmarnbelt about 17.6–18 km, Drogden 4.05 km, Świna tunnel 1.78 km
Three tunnels from the BrikBeam series. Sources: Femern A/S (2026), Wikipedia (Nov 2026), NBI 4/2023 and PORR (30 Jun 2023).

Clarifications

  • "6,820 segments": one website gave this figure, but it is a typo. 785 rings × 8 = 6,280 (GDDKiA/gov.pl).
  • "The tunnel is 3.2 km long": 3.2 km is the whole route with access roads; the tunnel itself is 1,780 m and the bored section 1,484 m.

What builders and investors can take from it

  • Groundwater decides the method and the cost. Freezing for 5 months is an extreme case, but the same principle applies to house foundations: a high water table means dewatering the dig, waterproofing and often a raft slab instead of strip footings.
  • Precast parts repeat, and repetition gives speed. 6,280 identical segments made about 8 m a day possible. On a small site, the equivalent is stock components instead of made-to-measure solutions on site.
  • Heat through walls counts too. In the episode we show the facade and insulation calculator: just as ground temperature is a design parameter in the tunnel, insulation thickness in a house translates into bills.

The episode and Shorts

The full episode is embedded above (Polish audio). Shorts on this topic: They froze the ground for 5 months to make a door, 785 rings: the machine built the tunnel itself, 38 m under the seabed, with ships sailing above the machine, 27 years of waiting for a tunnel in Świnoujście, A 900-million-zloty tunnel. What for?.

Other episodes with articles: Megaprojects: all BrikBeam episodes.

▶ Subscribe to BrikBeam on YouTube: construction worked out so you can check the maths.

Sources

  1. Nowoczesne Budownictwo Inżynieryjne 4/2023 (PORR article on the Świnoujście tunnel).
  2. PORR, press release on the tunnel opening, 30 Jun 2023.
  3. GDDKiA / gov.pl: releases of 13 Jul 2021 (halfway) and 12 Aug 2021 (1,000 m).
  4. inzynierbudownictwa.pl, "Tunel pod Świną przejezdny"; tunnelbuilder.
  5. money.pl, 3 Nov 2021 (ground freezing, lowest point, lanes).
  6. Bankier (start of boring, delay); Eurobuild CEE (pandemic, 95 days).
  7. Interia; Demagog (project history, ferry crossing time).
  8. PAP; gov.pl (cost and EU funding).
  9. TVP Info; Interia (Bielik ferries, sale of Bielik III).
  10. conadrogach.pl; Poland at Sea (ground conditions).
  11. Femern A/S (comparison with the Fehmarnbelt tunnel).

By the BrikBeam editorial team, 22 Nov 2026. The average boring rate and the cost per metre are our calculations from the source data. Spotted a mistake? Tell us via the contact form.

Advertisement
BB
BrikBeam construction calculators
3D floor plan, renovation, roof and facade estimates
🧮 INTERAKTYWNY KALKULATOR 2026

Szybki Kalkulator Kosztorysu Budowlanego

Oszacuj orientacyjny koszt robocizny, materiałów i narzutów dla swojego projektu w 15 sekund.

50 m²
Szacunkowy Kosztorys 2026
Szacowana robocizna: 47 500 kr
Materiały i sprzęt: 57 500 kr
Narzuty Kp + Zysk (sugerowane 18%): +18 900 zł
Łączny szacunek inwestycji:
90 750 kr
Zapisz ten kosztorys i wygeneruj ofertę PDF w BrikBeam Pro → ✓ 14 dni darmowego testu · Bez karty · Bez klucza USB
PAKIET WZORÓW DOKUMENTÓW 2026 (.DOCX & .XLSX)

Pobierz kompletny pakiet wzorów umów i protokołów budowlanych

Zyskaj natychmiastowy dostęp do prawnie sprawdzonych szablonów: Umowa o roboty budowlane, Umowa z podwykonawcą, Plan BIOZ, Protokół odbioru końcowego, Karta gwarancyjna i Harmonogram. Gotowe do edycji w Word i Excel.

✓ 100% zgodne z Kodeksem Cywilnym i Prawem Budowlanym ✓ Wzory z automatycznymi formułami w Excelu ✓ Możliwość natychmiastowego podpisu SMS w BrikBeam Pro
Pobierz cały pakiet wzorów bezpłatnie → Natychmiastowe pobranie · Dostęp 100% za darmo
Back to all articles
Share:
Advertisement
BB
BrikBeam construction calculators
3D floor plan, renovation, roof and facade estimates
Article link copied to clipboard!