🧱 Free concrete volume calculator

Concrete calculator – volume and cost of foundations

Tick the elements (strip footings, slab, pads, columns, walls), enter the dimensions and get m³ of concrete with allowance, truck loads, indicative ingredients for site-mixed C20/25, reinforcement steel and cost.

1. Concrete elements

2. Options

Cement bag (kg)

Result

Concrete to order
– m³
m³ net volume + % with allowance
Truck mixer loads
Concrete mass (2400 kg/m³)
Ready-mix C20/25 price per m³ (delivered) ()
Ready-mix cost
–
Unit prices are indicative (2026) and editable – enter your own shop or quote price.

Net volume

Elementm³steel kg

Ingredients for site-mixed C20/25

Indicative recipe per 1 m³: 350 kg CEM II 32.5 cement, 0.5 m³ sand (about 800 kg), 0.75 m³ gravel 2–16 mm (about 1200 kg), about 175 l water. A shopping list, not a mix design – for structural elements order certified ready-mix.

How we calculate

Volume of each element = product of its dimensions (pads and columns × count). Net sum × (1 + allowance) = concrete to order; trucks = volume ÷ capacity rounded up. Steel indicative: slab 80 kg/m³, strip and pad footings 60, columns 120, walls 70 kg/m³. Mass: 2400 kg/m³.

The calculator computes geometric volume. Concrete class, reinforcement and element thicknesses come from the structural design – the steel figure is only an order of magnitude for a preliminary estimate.

Advertisement
BB
BrikBeam construction calculators
3D floor plan, renovation, roof and facade estimates

How the calculator works – questions and answers

How much concrete do strip footings for a house need?

A 10 × 8 m house with a middle wall has about 44 m of footings. For a 0.6 × 0.4 m footing that is 44 × 0.6 × 0.4 = 10.6 m³ net, about 11.1 m³ with a 5 % allowance – two 8 m³ trucks or one 9 m³ truck plus a top-up. One metre of 0.6 × 0.4 m footing is 0.24 m³.

How many bags of cement per 1 m³ of concrete?

For site-mixed C20/25 (old B25) count about 350 kg of cement per 1 m³, i.e. 14 bags of 25 kg, plus about 0.5 m³ sand and 0.75 m³ gravel. Lean concrete C8/10 under footings needs about 200 kg (8 bags).

How much does 1 m³ of ready-mix cost in 2026?

In Poland ready-mix C20/25 costs roughly 380–480 PLN/m³ net plus delivery (150–300 PLN per truck) and an optional pump (600–1200 PLN/day). Prices depend on region and distance from the plant – enter the rate from your quote.

How much extra concrete should I order?

Usually 5 % for formed slabs and columns and 7–10 % for footings poured straight into the trench (uneven trench walls "eat" concrete). Better to top up than to run dry mid-slab.

How much does 1 m³ of concrete weigh and how much steel is needed?

Normal concrete weighs about 2400 kg/m³ (reinforced about 2500). Indicative steel usage: foundation slabs 60–100 kg/m³, strip footings 40–80, columns 100–150, walls 50–90 kg/m³. Exact quantities and bar sizes come from the structural design.

Need a contractor?Describe your job – free

The tool is free and runs in your browser – nothing is sent to a server.